solopisadas_10148.jpg
AP-9 Ferrol viaduct
Ferrol, La Coruña, Spain
Structural typology Road & Highway Bridges
Date December, 2002
Scope Detailed design and construction support
Cliente DRAGADOS S.A.
Construction DRAGADOS S.A.
Owner Ministerio de Fomento
Precast concrete beams with "in situ" concrete slab.
Total length: 1.168m / main span: 45m.
Pro
Precast concrete beams with "in situ" concrete slab.
Total length: 1.168m / main span: 45m.
AP-9 Ferrol viaduct
Ferrol, La Coruña, Spain
Structural typology Road & Highway Bridges
Date December, 2002
Scope Detailed design and construction support
Cliente DRAGADOS S.A.
Construction DRAGADOS S.A.
Owner Ministerio de Fomento
Precast concrete beams with "in situ" concrete slab.
Total length: 1.168m / main span: 45m.
aerea_10149.jpg
web_2_10150.jpg
obra_web_10151.jpg
location
Related projects