20210204_102352932_iOS_11019.jpg
Rehabilitation of the structure of Piers No. 1 and No. 2 at the San Diego Oil Terminal
A Coruña Harbour, Spain
Typologie Sea Structures
Date 2021-2026
Mission Repair project and technical support
Client Autoridad Portuaria de A Coruña
Maîtrise d'ouvrage Puerto de A Coruña
Both piers are located in the San Diego Oil Basin at the Inner Port of A Coruña, constructed in 1963 and 1965, respectively, with a separation of 155 m between them. The infrastructures consist of three reinforced concrete beam decks and an isostatic walkway, all simply supported on massive piers or piles (four prismatic piles per pier with a center-to-center distance of 23.35 m). The piles were built with prefabricated elements directly supported on a granular material bench on the rocky seabed.

The walkway consists of a prestressed concrete deck with a box-type cross-section.

The distance from shore to pier No. 1 is 55 m, and 65 m for pier No. 2. The width of the decks varies between 17.20 m and 16.20 m. Between the pier and the riprap, a deck of 14.80 m in length and 5.15 m in width is projected.









Pro
Both piers are located in the San Diego Oil Basin at the Inner Port of A Coruña, constructed in 1963 and 1965, respectively, with a separation of 155 m between them. The infrastructures consist of three reinforced concrete beam decks and an isostatic walkway, all simply supported on massive piers or piles (four prismatic piles per pier with a center-to-center distance of 23.35 m). The piles were built with prefabricated elements directly supported on a granular material bench on the rocky seabed.
The walkway consists of a prestressed concrete deck with a box-type cross-section.

The distance from shore to pier No. 1 is 55 m, and 65 m for pier No. 2. The width of the decks varies between 17.20 m and 16.20 m. Between the pier and the riprap, a deck of 14.80 m in length and 5.15 m in width is projected.








Rehabilitation of the structure of Piers No. 1 and No. 2 at the San Diego Oil Terminal
A Coruña Harbour, Spain
Typologie Sea Structures
Date Juin, 2025
Mission Repair project and technical support
Client Autoridad Portuaria de A Coruña
Maîtrise d'ouvrage Puerto de A Coruña
Both piers are located in the San Diego Oil Basin at the Inner Port of A Coruña, constructed in 1963 and 1965, respectively, with a separation of 155 m between them. The infrastructures consist of three reinforced concrete beam decks and an isostatic walkway, all simply supported on massive piers or piles (four prismatic piles per pier with a center-to-center distance of 23.35 m). The piles were built with prefabricated elements directly supported on a granular material bench on the rocky seabed.

The walkway consists of a prestressed concrete deck with a box-type cross-section.

The distance from shore to pier No. 1 is 55 m, and 65 m for pier No. 2. The width of the decks varies between 17.20 m and 16.20 m. Between the pier and the riprap, a deck of 14.80 m in length and 5.15 m in width is projected.









20210204_111732428_iOS_11022.jpg
20210204_112509800_iOS_11023.jpg
20210204_112839118_iOS_11024.jpg